In the Greater Toronto Area, construction schedules rarely stop between November and April. However, pouring ready-mix concrete in cold weather requires strict adherence to CSA A23.1:24 and the 2024 Ontario Building Code (OBC 9.3.1.9) to prevent early-age freezing, delayed strength gain, and surface scaling.   


What Counts as Cold-Weather Concreting in Ontario?

Under CSA A23.1:24, cold-weather concreting protocols apply whenever there is a probability of the ambient air temperature falling below 5°C within 24 hours of placement. When temperatures drop, cement hydration slows dramatically. If fresh concrete freezes before reaching a minimum compressive strength of 7.0 MPa, ice expansion permanently disrupts the cement paste matrix, causing irreversible strength loss.   


Mandatory Placement Temperatures (CSA A23.1:24 Table 14)

At ML Group's Toronto batch plant, our natural-gas steam heating system warms mixing water and aggregates prior to dispatch so your load arrives within compliant CSA placement windows:

  • Thin sections (< 0.3 m, such as slabs and driveways): Minimum 10°C, Maximum 32°C

  • Medium sections (0.3 m to < 1.0 m, such as foundation walls): Minimum 10°C, Maximum 30°C

  • Thick sections (1.0 m to < 2.0 m): Minimum 5°C, Maximum 25°C

  • Mass concrete (>2.0 m): Minimum 5°C, Maximum 20°C


Specifying the Right Winter Mix: Otimo Artico & Otimo Acel

Ordering standard summer mixes in January leads to long finishing windows and extended heating costs. Pair heated concrete with ML Group's Otimo winter performance series:

  • Otimo Artico: Engineered for sub-zero GTA pours, lowering the freezing point of mixing water while maintaining workability without adding jobsite water.

  • Otimo Acel: Non-chloride set accelerator that speeds up initial set and early strength gain so crews can finish slabs on schedule and hit the 7.0 MPa frost-protection threshold faster. (Never use calcium chloride in reinforced concrete or galvanized forms, as it accelerates rebar corrosion.)


Jobsite Winter Pour Checklist for GTA Contractors

  1. Thaw the Subgrade & Forms: Never place concrete onto frozen ground, snow, or ice. Large temperature differentials between cold granular base and warm concrete cause slab blistering and delamination.   

  2. Maintain 10°C Curing: Keep placed concrete at greater than 10°C for at least 3 days (basic curing) or 7 days for Class C-2 exterior flatwork using insulated tarps or heated enclosures.   

  3. Protect Test Cylinders: Field-cast strength cylinders must be stored in heated jobsite curing boxes at 15°C to 25°C during the first 24 hours so lab breaks accurately reflect in-place structural strength.   


Need heated ready-mix concrete dispatched anywhere in Toronto or the GTA? Download our Cold-Weather Concreting Spec Sheet or request a winter mix quote online—or call our dispatch desk directly at (416) 603-7878.